NEC Downloads & Publications
Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

GMH Planning/CECA NEC4 Bulletins – Master List

Please find below a current list of the monthly CECA/GMH bulletins that have been issued to date, in order of most recently issued.

CECA NEC4 Bulletins – Master List

  1. Finishing/closing down a project under an NEC contract – CECA Bulletin 68
  2. Start up guide/early stages for an NEC contract – CECA Bulletin 67
  3. X22 Early Contractor Involvement (ECI) – CECA Bulletin 66
  4. Behaviours under NEC Contracts- CECA Bulletin 65
  5. Producing Better Scope- CECA Bulletin 64
  6. Dividing Date – CECA Bulletin 63
  7. Amending/revising an Activity Schedule – CECA Bulletin 62
  8. Acceptance: what does it mean? – CECA Bulletin 61
  9. CECA Rates for Equipment – CECA Bulletin 60
  10. Lack of Response, Time-Bars and Deemed Acceptances in NEC Contracts – CECA Bulletin 59
  11. Ten Top Tips for Managing NEC Contracts Effectively – CECA Bulletin 58
  12. Project Controls alongside an NEC contract programme – CECA Bulletin 57
  13. Programme narrative when submitting a programme for acceptance – CECA Bulletin 56
  14. Check list before signing a NEC contract – CECA Bulletin 55
  15. Termination – CECA Bulletin 54
  16. Pricing and Payment under Main Option B (Priced Contract with Bill of Quantities)- CECA Bulletin 53
  17. NEC4 ECC High Level User Guide- CECA Bulletin 52
  18. Assessing Compensation Events: Forecast or Actual Cost? – CECA Bulletin 51
  19. Role of Records Alongside Administering NEC Contracts (Ben Walker & Glenn Hide) – CECA Bulletin 50
  20. Programme at Tender Stage – CECA Bulletin 49
  21. Assessing Weather Delays under NEC Contracts – CECA Bulletin 48
  22. Requests for Information (RFI) and/or Technical Query (TQ) in Relation to NEC Contracts – CECA Bulletin 47
  23. Concurrency and NEC Contracts – CECA Bulletin 46
  24. NEC Supply Contract – CECA Bulletin 45
  25. Professional Service Contract – CECA Bulletin 44
  26. State of the Industry Survey 2024 Results – CECA Bulletin 43
  27. A Positive Approach to Early Warnings – CECA Bulletin 42
  28. X20 Key Performance Indicators (KPIs) – CECA Bulletin 41
  29. Secondary Option “Y” Clauses (Glenn Hide & Barry Trebes) – CECA Bulletin 40
  30. Role of the Project Manager – CECA Bulletin 39
  31. Z Clauses That Could Significantly Alter Risk Profile – CECA Bulletin 38
  32. Top Ten NEC4 ECC Clauses – CECA Bulletin 37
  33. Payments – CECA Bulletin 36
  34. Common Misconceptions Associated when Administering NEC Contracts – CECA Bulletin 35
  35. Periods for response in NEC contracts – CECA Bulletin 34
  36. Dictionary definitions versus contractual definitions – CECA Bulletin 33
  37. Engineering and Construction Short Contract (ECSC) – CECA Bulletin 32 – Engineering and Construction Short Contract (ECSC)
  38. Disallowed Costs – CECA Bulletin 31
  39. Contractual Milestones to Show on a Programme – CECA Bulletin 30
  40. Focus on Engineering and Construction Contract (ECC) options E & F – CECA Bulletin 29
  41. Focus on Engineering and Construction Contract (ECC) options C & D – CECA Bulletin 28
  42. Focus on Engineering and Construction Contract (ECC) option B – CECA Bulletin 27
  43. Focus on Engineering and Construction Contract (ECC) option A – CECA Bulletin 26
  44. Secondary Option X1: Price Adjustment for Inflation – CECA Bulletin 25
  45. Communication Flow – CECA Bulletin 24
  46. Payment, Defined Cost and Schedule of Cost Components – CECA Bulletin 23
  47. Project audits and contractual health checks – CECA Bulletin 22
  48. CECA Bulletin 21 – Role of the Supervisor
  49. CECA Bulletin 20 – Managing Subcontractors
  50. CECA Bulletin 19 – Dispute Resolution Process
  51. CECA Bulletin 18 – Clause 63.5 and assessing a compensation event against the last Accepted Programme
  52. CECA Bulletin 16 – Quality Management & Managing Defects
  53. CECA bulletin 17 – Showing non-implemented compensation events on the programme
  54. CECA NEC4 Bulletin 15: Getting compensation events implemented
  55. CECA NEC4 Bulletin 14: Spirit of mutual trust and cooperation
  56. NEC4 CECA Bulletin No 13: Notifying early warnings and notifying compensation events
  57. NEC4 CECA Bulletin No 12: Use of cloud-based systems to manage NEC contracts
  58. NEC4 CECA Bulletin No 11: Contract Data parts 1 & 2
  59. NEC4 CECA Bulletin No 10: Float Types and Ownership
  60. NEC4 CECA Bulletin No 9: Contractor Proposals and Whole Life Cost Savings
  61. NEC4 CECA Bulletin No 8: Programmes with compensation event quotations
  62. NEC4 CECA Bulletin No 7: Instructions from Project Managers and associated delegation of powers
  63. NEC4 CECA Bulletin No 6: The importance of a regular Accepted Programme
  64. NEC4 CECA Bulletin No 5 – Early warnings and the liability for not notifying them
  65. NEC4 CECA Bulletin No4 – Compensation Event Quotations and use of Assumptions
  66. CECA/GMH Bulletin 3 – ECC Secondary Options
  67. Key Dates – NEC4 CECA Bulletin #2
  68. NEC4 CECA bulletin No 1 – Z clauses
chevron_left
chevron_right
attero-rocketcaret-downclosefacebook-squarehamburgerinstagram-squarelinkedin-squarepauseplaytwitter-square