Please find below a current list of the monthly CECA + GMH bulletins that have been issued to date, in order of most recently issued.
CECA NEC4 Bulletins – Master List
- Programme at tender stage – CECA Bulletin 49
- Assessing Weather Delays under NEC Contracts – CECA Bulletin 48
- Requests for Information (RFI) and/or Technical Query (TQ) in Relation to NEC Contracts – CECA Bulletin 47
- Concurrency and NEC Contracts – CECA Bulletin 46
- NEC Supply Contract – CECA Bulletin 45
- Professional Service Contract – CECA Bulletin 44
- State of the Industry Survey 2024 Results – CECA Bulletin 43
- A Positive Approach to Early Warnings – CECA Bulletin 42
- X20 Key Performance Indicators (KPIs) – CECA Bulletin 41
- Secondary Option “Y” Clauses (Glenn Hide & Barry Trebes) – CECA Bulletin 40
- Role of the Project Manager – CECA Bulletin 39
- Top 10 Z Clauses That Could Significantly Alter Risk Profile – CECA Bulletin 38
- Top Ten NEC4 ECC Clauses – CECA Bulletin 37
- Payments – CECA Bulletin 36
- Common Misconceptions Associated when Administering NEC Contracts – CECA Bulletin 35
- Periods for response in NEC contracts – CECA Bulletin 34
- Dictionary definitions versus contractual definitions – CECA Bulletin 33
- Engineering and Construction Short Contract (ECSC) – CECA Bulletin 32 – Engineering and Construction Short Contract (ECSC)
- Disallowed Costs – CECA Bulletin 31
- Contractual Milestones to Show on a Programme – CECA Bulletin 30
- Focus on Engineering and Construction Contract (ECC) options E & F – CECA Bulletin 29
- Focus on Engineering and Construction Contract (ECC) options C & D – CECA Bulletin 28
- Focus on Engineering and Construction Contract (ECC) option B – CECA Bulletin 27
- Focus on Engineering and Construction Contract (ECC) option A – CECA Bulletin 26
- Secondary Option X1: Price Adjustment for Inflation – CECA Bulletin 25
- Communication Flow – CECA Bulletin 24
- Payment, Defined Cost and Schedule of Cost Components – CECA Bulletin 23
- Project audits and contractual health checks – CECA Bulletin 22
- CECA Bulletin 21 – Role of the Supervisor
- CECA Bulletin 20 – Managing Subcontractors
- CECA Bulletin 19 – Dispute Resolution Process
- CECA Bulletin 18 – Clause 63.5 and assessing a compensation event against the last Accepted Programme
- CECA Bulletin 16 – Quality Management & Managing Defects
- CECA bulletin 17 – Showing non-implemented compensation events on the programme
- CECA NEC4 Bulletin 15: Getting compensation events implemented
- CECA NEC4 Bulletin 14: Spirit of mutual trust and cooperation
- NEC4 CECA Bulletin No 13: Notifying early warnings and notifying compensation events
- NEC4 CECA Bulletin No 12: Use of cloud-based systems to manage NEC contracts
- NEC4 CECA Bulletin No 11: Contract Data parts 1 & 2
- NEC4 CECA Bulletin No 10: Float Types and Ownership
- NEC4 CECA Bulletin No 9: Contractor Proposals and Whole Life Cost Savings
- NEC4 CECA Bulletin No 8: Programmes with compensation event quotations
- NEC4 CECA Bulletin No 7: Instructions from Project Managers and associated delegation of powers
- NEC4 CECA Bulletin No 6: The importance of a regular Accepted Programme
- NEC4 CECA Bulletin No 5 – Early warnings and the liability for not notifying them
- NEC4 CECA Bulletin No4 – Compensation Event Quotations and use of Assumptions
- CECA/GMH Bulletin 3 – ECC Secondary Options
- Key Dates – NEC4 CECA Bulletin #2
- NEC4 CECA bulletin No 1 – Z clauses