---
title: Programme and Planning
type: taxonomy_archive
taxonomy: category
slug: programme-and-planning
term_id: 37
permalink: "https://gmhplanning.co.uk/category/programme-and-planning/"
post_count: 21
---

# Programme and Planning

Posts in this archive: 21

- [NEC4 Webinar No.7 - Understanding Contract Data](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/nec4-understanding-contract-data.md)
- [NEC4 Webinar No.5 - Programme: Getting it Right](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/nec4-webinar-programme-getting-it-right.md)
- [NEC4 Webinar - Managing Subcontractors (SE1EP2)](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/webinar-18th-november-managing-subcontractors.md)
- [NEC Guidance Notes - An Introduction](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/guidance/introduction.md) — An introduction to GMH Planning's NEC guidance notes, a useful  resource at all levels for those involved in projects under the NEC3 & NEC4 forms of contract.
- [There is no such thing as concurrency under an NEC Contract!](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/no-such-thing-as-concurrency-under-nec-contracts.md)
- [Negative Float on an NEC Contract Programme](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/negative-float-on-an-nec-contract-programme.md)
- [Benefits of a programme at tender stage](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/nec-contract-programme-at-tender-stage.md)
- [Which programme should be used as the "baseline"?](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/nec4-programme-baseline.md)
- [NEC Option A - Don't Get Caught Out](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/nec-option-a.md)
- [Compensation Events - Good Practice Guide](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/downloads/compensation-events-good-practice-guide.md)
- [NEC3 LinkedIn Conference: Compensation Events - Good Practice Guide](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/nec3-linkedin-conference-compensation-events-good-practice-guide.md)
- [Assessing compensation events - which programme should you use?](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/assessing-compensation-events-which-programme-should-you-use.md)
- [New article on the use of the programme within NEC3](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/new-article-on-the-use-of-the-programme-within-nec3.md)
- [ECC Clause 60.1 - Compensation Events](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/guidance/ecc-clause-60-1-compensation-events.md)
- [ECC Clause 31.3 - Programme Acceptance](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/guidance/ecc-clause-31-3-programme-acceptance.md)
- [ECC Clause 31.2 - Programme Requirements](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/guidance/ecc-clause-31-2-programme-requirements.md)
- [ECC Section 14 - Project Manager and Supervisor](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/guidance/ecc-clause-14-project-manager-and-supervisor.md)
- [ECC Section 3 - Programme](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/guidance/nec3-ecc-clause-30-programme.md) — The NEC suite of contracts puts far greater contractual requirements upon the Contractor to produce and manage a detailed programme than other forms of contract currently in existence within the construction industry. Clear contractual mechanisms for agreeing change between the parties are key to successs.
- [ECC Section 13 - Communications](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/guidance/nec3-ecc-clause-13-communications.md)
- [NEC requirement to act in a  "spirit of mutual trust and co-operation"](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/guidance/nec3-contract-ecc-clause-10-1-spirit-of-mutual-trust.md) — The opening clause of the ECC contract brings two very important issues to the fore, that 1) everyone named and involved with the contract has to do what it says, and 2) do this in a spirit of mutual trust and cooperation.
- [Think before you Z clause...](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/post/think-before-you-z-clause.md)
