What do you price at tender stage – the Bill of Quantities or the Works Information?

An item that is included within the works information is clearly missing from the bill of quantities. How is this managed under an ECC form of contract?

ECSS

Managing a programme under the NEC form of contract

A well thought out, detailed contractor’s programme should be used such that is a proactive management tool for both managing the works on a day-to-day basis, and a mechanism to demonstrate the effects and hence entitlement (if any) when change occurs.

ECSS

Programme effects of an early warning

NEC3 used to require that the effect of notified early warnings should be shown on a programme issued for acceptance, before that requirement was deleted in the June 2006 amendments. What does this mean in terms of what should be shown on the programme in terms of early warnings?

ECSS

Producing an NEC3 Programme

A well thought out, detailed contractor’s programme should be used such that is a proactive management tool for both managing the works on a day-to-day […]

ECSS

Programming non-implemented compensation events

What should a programme issued for acceptance contractually be showing in terms of implemented and non-implemented compensation events?

ECSS

Compensation events and movement in Completion Date

When compensation event quotations take a long time to get accepted, it may create a difference between planned Completion and Completion Date that in the interim neither party are necessarily clear on whose liability that is…

ECSS

Contractors’ Float in NEC ECC Programmes

A common question is “who owns the float” on a project, but first you have to understand what float you are talking about. Different types of float under an ECC contract have different owners, which this article will explore.

ECSS

Programming under an NEC contract

Programme management is essential on an ECC contract. Both parties have to understand their contractual obligations to keep on top of this process, so that the transparency that the NEC contract is trying to create is achieved for the benefit of both parties.