title: The importance of always having a regularly Accepted Programme in place
date: 2017-01-26T18:59:49Z
modified: 2024-03-01T09:49:14Z
permalink: "https://gmhplanning.co.uk/nec-downloads/importance-always-regularly-accepted-programme-place/"
type: downloads
status: publish
excerpt: ""
wpid: 1934
nec_contract_type:
  - NEC3
  - NEC4
nec_contract_version:
  - NEC Engineering & Construction Contract (ECC)
download_category:
  - Programme
featured_image: "https://gmhplanning.co.uk/wp-content/uploads/2022/01/NEC4-Engineering-and-Construction-Contract.jpg"
featured_image_alt: NEC4 Engineering and Construction Contract
author: Glenn Hide
timestamp: 2024-03-01T09:49:14Z
tags:
  - NEC3
  - NEC4
  - NEC Engineering & Construction Contract (ECC)
  - Programme
---

Here is an article that has gone into the NEC3 Usergroup newsletter which looks at some of the reasons that programmes are not accepted and why it is so important to overturn this trend. It considers six common reasons for rejection and considers their validity and how both parties can/should prevent this from happening, as a regular Accepted Programme should be both Parties priority on a project.

[The importance of always having a regularly accepted programme](https://gmhplanning.co.uk/wp-content/uploads/2017/01/The-importance-of-always-having-a-regularly-accepted-programme.pdf)[Download](https://gmhplanning.co.uk/wp-content/uploads/2017/01/The-importance-of-always-having-a-regularly-accepted-programme.pdf)

## Topics

**NEC Contract Editions:** [NEC3](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/nec_contract_type/nec3.md), [NEC4](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/nec_contract_type/nec4.md)

**NEC Contract Versions:** [NEC Engineering & Construction Contract (ECC)](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/nec_contract_version/nec-engineering-construction-contract-ecc.md)

**Download Categories:** [Programme](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/programme.md)