Here is a summary of some of the key changes that are coming within the NEC4 contracts when they are launched at the end of June this year.
Some very welcome inclusions that should enhance even further the benefits and practicalities that these contracts are trying to achieve for the industry. Some of the headline elements that I personally have been wanting to see that have been changed include the name of the “Risk Register” changed to “Early Warning Register”, the potential for there to be a deemed acceptance of the programme where PM does not respond, clarity on showing non-implemented compensation events on programme, as well as some fairly major changes to the SCC/SSCC. The summary picks up the main changes that I think you will be very interested to know: