Professional Service Contract: CECA Bulletin 44

The NEC family include contracts for a variety of different contractual arrangements that could be necessary on a project. Term Service Contracts are intended to […]

Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

A Positive Approach to Early Warnings – CECA Bulletin 42

Next month we will be issuing a very important bulletin sharing a review of the ‘state of the industry’ regarding the practical application and experience […]

Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

X20 Key Performance Indicators (KPIs) – CECA Bulletin 41

NEC X20 Key Performance Indicators (KPIs) allow a Client to create performance measurements to encourage a Contractor to act or perform in a certain way to help achieve wider Client objectives.

Image for NEC Training Course 1 NEC3 NEC4 Overview and Introduction to the ECC by GMH Planning Ltd

NEC3/NEC4 Overview and Introduction to the ECC

This one-day NEC3/NEC4 ECC overview training workshop introduces the common philosophies. key mechanics and provisions of the ECC.

  • 7 hours 15 mins Course duration
  • £ POA Price
  • Classroom, Online Delivery mode
Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

Role of the Project Manager – CECA Bulletin 39

The Engineering and Construction Contract (ECC) is an agreement between the Client and the Contractor as the named Parties. The contract goes on to identify […]

NEC3 and NEC4 Guidance Notes – An Introduction

NEC Guidance Notes – An Introduction

An introduction to GMH Planning’s NEC guidance notes, a useful  resource at all levels for those involved in projects under the NEC3 & NEC4 forms of contract.

NEC Miscellaneous FAQs

FAQ: Miscellaneous

Frequently asked questions around other aspects of NEC contracts not covered in our other categories.

NEC Frequently Asked Questions on NEC Compensation Events

FAQ: NEC Compensation Events

Frequently asked questions around section six of the contract which are compensation events.

NEC Frequently Asked Questions on NEC Programme

FAQ: NEC Programme

Frequently asked questions about section 3 of the contract which is “time” and all things programme.

GMH Public Training Workshops FAQs

FAQ: Public Training Workshops

GMH NEC Training Courses FAQs

FAQ: NEC Training Courses

Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

Z clauses that could significantly alter risk profile – CECA Bulletin 38

Although the NEC Contract was meant in its base form to be applicable for all construction projects some Clients may still feel the need to […]

NEC Frequently Asked Questions on NEC Payments

FAQ: NEC Payments

Frequently asked questions around section five of the contract and payments.

NEC FAQs on NEC Early Warnings

FAQ: NEC Early Warnings

Frequently asked questions around early warnings, which are a simple yet often misunderstood process within NEC contracts.

NEC Frequently Asked Questions on NEC Testing and Defects

FAQ: NEC Testing and Defects

Frequently asked questions on testing and defects.

NEC Contract Documents & Contract Data FAQs

FAQ: NEC Contract Documents and Contract Data

Frequently asked questions about NEC Contract documents and Contract Data.

NEC Main & Secondary Options FAQs

FAQ: NEC Main & Secondary Options

Frequently Asked Questions on NEC Contract Main & Secondary Options.

Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

Top Ten NEC4 ECC Clauses – CECA Bulletin 37

For many people trying to understand a contract can appear to be a bit daunting and even unnerving given some of the unfamiliar language that […]

Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

CECA Bulletin 31 – Disallowed Costs

NEC Contract focus month 31 – Disallowed Costs Within options C, D,E & F of the NEC4 Engineering and Construction Contract (ECC), the Contractor is […]

Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

CECA Bulletin 30 – Contractual milestones to show on a programme

The current forms of contract within the NEC family place a much greater significance on the importance of the programme and on the specific content […]

Cover image for CECA NEC4 Bulletin CECA Member Briefings by GMH Planning Ltd

CECA Bulletin 24 – Communication Flow

Good communication is at the heart of any well managed project and NEC contracts have always looked to promote this within their contractual processes. Section […]