Introduction
This overview is intended to be a quick reference guide as to where a particular subject matter can be found within the contract. This guide focuses on the most commonly used and relevant day to day clauses likely to be most relevant. For a specific project, any bespoke clause amendments introduced by a Client would have to be taken into account. Sections 1-9 are the core clauses for every TSC option A-E contract, with option specific clause details.
Section 1 – General
Actions
- 10.1
- Reminder that all Parties are to act as stated in the contract
- 10.2
- Obligation to also act in a spirit of mutual trust and cooperation.
- 11.2
- List of defined terms (in alphabetical order).
Communications
- 13.1
- All communications in a form that can be read, copied and recorded.
- 13.2
- Communications are only valid if submitted by the system stated in Scope.
- 13.3
- Responses within period for reply or as stated in contract.
- 13.5
- Service Manger may extend period for reply by agreement.
- 13.7
- Any notification has to be separate from any other communication.
Service Manger (SM)
- 14.1
- Service Manger acceptance does not transfer liability from Contactor.
- 14.2
- Service Manger must formally delegate actions in writing.
- 14.3
- Service Manger can issue instructions to change the Scope.
- 14.5
- Service Manager gives an instruction to correct Price List.
Early Warnings
- 15.1
- Reasons for which an early warning should be notified.
- 15.2
- Either party can instruct the other to an early warning meeting.
- 15.3
- Actions expected of all parties at an early warning meeting.
- 15.4
- Updating of the Early Warning Register by the Service Manger.
Contractor’s Proposals
- 16.1
- Contractor can propose value engineering to reduce Prices.
- 16.2
- Service Manager responds to value engineering proposal within 4 weeks.
- 16.3
- Contractor may propose a change to Working Areas.
Ambiguities
- 17.1
- Notifying and resolving of an ambiguity between contract documents.
- 17.2
- Notifying and resolving of an illegal or impossible requirement.
Task Orders
- 19.1
- details of Task Order issued by Service Manager for Contractor to quote
- 19.2
- Contractor submits (within 3 weeks) and SM responds (2 weeks) to quote
- 19.3
- Service Manager may instruct revised Task Order quote
- 19.4
- Extension to produce quote may be granted by Service Manager
- 19.5
- Service Manager may assess and notify pricing for a Task if not agreed.
- 19.6
- Task prices may be assessed from Price List or as a compensation event.
- 19.7
- Delay damages may be applicable if Task Completion Date exceeded.
- 19.8
- Task price list added to Price List and work added to Scope once issued.
Section 2 – Contractors Responsibilities
Providing the Works
- 20.1
- Contractor obligation to Provide the Works in accordance with Scope.
- 20.2
- Contractor minimises interference caused to Affected property.
Design of Equipment
- 20.1
- Contractor to submit details of design of Equipment if instructed by SM.
People
- 21.1
- Contractor to provide key person(s) stated in CD2 or suitable replacement.
- 21.2
- Service Manger can instruct Contractor to remove any person.
Working with Client and Others
- 23.1
- Requirement for Contractor to work with Others as instructed/in Scope.
- 23.2
- Contractor and Client provides services and other things stated in Scope.
Subcontracting
- 24.2
- Requirement to submit proposed Subcontractor for acceptance by SM.
- 24.2
- Reasons under which SM could not accept a Subcontractor.
- 24.3
- Also have to submit subcontractor terms for acceptance by SM.
Other responsibilities
- 25.3
- Contractor obeys instructions given in accordance with contract by SM.
- 25.4
- Contractor acts in accordance with Health & Safety as stated in Scope.
Disclosure
- 27.2
- Contractor may only publicise works with Client’s agreement.
Section 3 – Programme
Starting Date / Completion Date
- 30.1
- Contractor does not start work on site until the starting date.
- 30.2
- Contractor does not start work on a Task until Task Order issued by SM.
- 30.3
- Service Period may be extended to include completion of a Task.
The Contractor’s Plan
- 31.1
- Requirement for Contractor to submit first plan for acceptance.
- 31.2
- Detailed list of what is required to be shown on plan for acceptance.
- 31.3
- Reasons for SM not to accept a plan and potential for deemed acceptance.
Revising the Contractor’s Plan
- 32.1
- List of what should be shown on a revised plan
- 32.2
- Intervals for revised plan submissions to Service Manager.
Task Order Programme
- 33.1
- Task Order programme submitted within period stated in Contract Data
- 33.2
- Detailed list as to what is required to be shown on Task Order programme.
- 33.3
- Reasons for SM not to accept programme/potential for deemed acceptance.
Revising Task Order Programme
- 34.1
- Requirements to show on each revised Task Order programme.
- 34.2
- Revised Task Order programme as instructed or when Contractor chooses access.
Access
- 35.1
- Client provides access to Affected Property as shown on plan/programme.
Instruction to Stop or Not Start Work
- 36.1
- SM may instruct to stop or not start work and to restart/remove from Scope.
Section 4 – Quality Management
Quality Management System
- 40.1
- Contractor operates a quality management system in line with Scope.
- 40.2
- Quality policy statement and plan issued for Service Manager acceptance.
- 40.3
- Service Manager may instruct correct failure to comply with quality plan.
Tests and Inspections
- 41.1
- Requirement to carry out tests and inspections as per Scope/applicable law.
- 41.3
- Requirement to notify Service Manager prior to tests being carried out.
- 41.5
- Requirement for Service Manager to carry out tests/inspections
- 42.1
- Requirement to carry out tests prior to delivery where required.
Notifying/Correcting Defects
- 43.1
- Either party notify each other as soon as become aware of a defect.
- 43.2
- Contractor obligation to correct defect whether notified or not.
- 43.3
- Contractor corrects defect within time that minimises impact.
- 43.4
- Service Manager/Client arranges access to correct a defect if needed.
Accepting Defects
- 44.1
- Can propose for defect to not be corrected and Scope changed accordingly.
- 45.2
- Contractor to submit resultant quotation saving to SM to accept/not accept.
Section 5 – Payment
Assessing the amount due
- 50.1
- Service Manager to assess the amount due at each assessment date.
- 50.2
- Requirement to submit application before each application date.
- 50.3
- Defines the amount due in any application.
- 50.4
- If Contractor not submit application on time SM will assess at zero.
- 50.5
- 25% PWDD can be withheld if no 1st accepted plan.
- 50.6
- SM corrects any incorrectly paid amounts in next assessment.
Payment
- 51.1
- Service Manger to certify payment within 1week of assessment date.
- 51.2
- Confirmation of period within which payment should be made.
- 51.3
- Interest recoverable on items corrected on a later certificate.
- 51.4
- interest recoverable on late payments.
Defined Cost
- 52.1
- Any Contractors costs not identified in Defined Cost are in the Fee.
Final Assessment
- 53
- Section on how/when final assessment is made at end.
Section 6 – Compensation Events
Compensation Events (CE)
- 60.1
- List of what events would be valid compensation events (18 reasons).
Notification
- 61.1
- SM can notify compensation event at time of issuing instruction.
- 61.2
- SM instructs Contractor to produce quotation (and proceed in meantime).
- 61.3
- Contractor can notify a CE and can be time barred after a period if late.
- 61.4
- SM to accept or not accept if Contractor has notified a CE.
- 61.4
- Deemed acceptance if the SM does not respond to reminder.
- 61.5
- SM can advise that an early warning could have been given which wasn’t.
- 61.6
- SM can state assumptions for Contractor to base the quote upon.
- 61.7
- No compensation events can be issued eight weeks after Service Period.
Quotations
- 62.1
- SM can request alternative quotations for dealing with a CE.
- 62.2
- Contractor to provide a quote and alterations to programme (if relevant).
- 62.3
- Contractor to provide quote within 3 weeks, SM response within 2 weeks.
- 62.4
- Service Manger can instruct a revised quote (after explaining why).
- 62.5
- Service Manger can extend period for Contractor to produce quote.
- 62.6
- Contractor’s quote deemed accepted if no response to reminder.
Assessment
- 63.1
- Price List rates used if CE only affects quantities in Price List.
- 63.2
- Basis of quotes in relation to if should be actual or forecast defined cost.
- 63.3
- May be agreed to use rates or lump sums to assess change to Prices.
- 63.4
- Prices are not reduced unless otherwise stated in contract.
- 63.5
- States the only CE reasons which would reduce the Prices.
- 63.6
- Definition of reasons for contractual movement in Task Completion Date.
- 63.8
- SM may assess as though early warning had been given if it wasn’t.
- 63.9
- Rules for allocation of risk within a compensation event quotation.
- 63.10
- Requires Contractor to act promptly and competently to a CE.
- 63.11
- Ambiguities assessed in favour of Party that did not provide the Scope.
Service Manger’s Assessments
- 64.1
- Reasons under which SM can make own assessment of a CE.
- 64.2
- SM may assess plan for remaining work in assessing a CE.
- 64.3
- SM to notify Contractor of their own assessment of a CE.
- 64.4
- Deemed acceptance if SM no response to a notification of no assessment.
Proposed Instructions
- 65.1
- Service Manager can instruct a quotation for proposed instruction.
- 65.2
- Contractor submits quotation within 3 weeks and SM to respond.
- 65.3
- If quotation not accepted SM can still instruct (and then assessed as CE).
Implementation
- 66.1
- Implemented when CE accepted/assessed/deemed accepted.
- 66.2
- Prices/Completion Date changed accordingly following agreement.
- 66.3
- Compensation event quote is not changed if later found to be wrong.
Section 7 – Use of Equipment, Plant and Materials
- 70.1
- Title of materials transfers from Contractor to Client once in Service Area
- 71.1
- Contractor has right to use Client equipment, Plant and Materials
- 71.2
- Contractor returns Client equipment, Plant/Materials end of Service period
- 72.1
- Contractor has right to use material provided by Client to Provide Service
Section 8 – Risks and Insurance
- 80.1
- List of Client’s liabilities.
- 81.1
- List of Contractor’s liabilities
- 83
- Insurance cover details
- 84
- Insurance policies and who needs to provide what to whom.
Section 9 – Termination
- 90.2
- Termination table showing party/reason/procedure/amount due
- 91.1
- List of valid reasons for termination
- 92
- Procedures to follow upon termination
- 93
- Payment upon termination
Additional Option A clauses
- 11.2
- Option A specific identified and defined terms.
- 31.4
- Requirement for activity schedule to relate to items on plan/ programme.
- 55.1
- Clarifies that information in Price List is not Scope.
- 55.3
- Contractor may submit revised Price List for acceptance.
- 55.3
- Reasons SM has for not accepting a revised Price List
- 60.2
- Reasons when change to Price List may reduce Prices
- 63.12
- Adjustment of Prices in line with value engineering percentage
- 63.15
- Ascertaining a new People Rate where required.
Additional Option C clauses
- 11.2
- Option C specific identified and defined terms.
- 20.4
- Contractor provides forecast of total Defined Cost at contract intervals.
- 24.4
- Contractor to submit pricing information for each subcontractor.
- 41.7
- Liability of costs for carrying out repeat test or inspection.
- 50.7
- Payments in other currencies.
- 50.9
- Opportunity for finalising Defined Costs for part of the works.
- 52.3
- Requirement for Contractor to keep records.
- 54.1/2
- SM assesses Contractor’s share of the Prices and actual defined cost.
- 54.3
- assessment of Contractor’s share following Completion.
- 55.1
- Clarifies that information in Price List is not Scope
- 60.2
- Reasons when change to Price List may reduce Prices
- 63.13
- Prices are not reduced if it was a Contractor idea to reduce defined cost
- 93.3/4
- Rules on assessing share in event of termination of the contract.
Additional Option E clauses
- 11.2
- Option E specific identified and defined terms
- 20.4
- Contractor provides forecast of total Defined cost at contract intervals.
- 24.4
- Contractor to submit pricing information for each subcontractor.
- 50.8
- Payments in other currencies.
- 50.9
- Opportunity for finalising Defined Costs for part of the works.
- 52.2
- Requirement for Contractor to keep records.
- 52.3
- SM may inspect Contractor records at any time within working hours.
Secondary Options
X1 – Price Adjustment for Inflation
- X1.1
- Defined terms – Base Date Index, Latest Index, Price Adjustment Factor.
- X1.2
- How Price Adjustment Factor is applied.
- X1.3/4
- Price adjustment for amount due.
- X1.5
- Defined cost for compensation events.
X2 – Changes in law
- X2.1
- CE if occurs after the Contract Date.
X3 – Multiple Currencies
- X3.1/2
- Payment and exchange rates.
X4 – Ultimate Company Guarantee
- X4.1/2
- Given within 4 weeks of Contract Date.
X10 – Information Modelling
- X10.1
- Defined terms.
- X10.2
- Contractor collaborates with other Information Providers
- X10.3
- Early warning requirement for anything could impact Information Model
- X10.4
- Submission of Information Execution Plan.
- X10.5
- Compensation events.
- X10.6
- Use of the Information Model X10
- X10.7
- Client and Consultant liabilities.
X11 Termination by Client
- X11.2
- Procedures and amount due to be paid.
X12 – Multiparty Collaboration
- X12.1
- Identified and defined terms.
- X12.2
- Actions to be taken by Partners and Core Group.
- X12.3
- Collaboration by all Parties.
- X12.4
- Incentives – amounts paid to Partner if KPI(s) achieved.
X13 Performance Bond
- X13.1
- Required as stated in CD1.
X17 Low Service Damages
- X17.1
- For defects that miss performance levels.
X18 – Limitation of Liability
- X18.1-3
- Limits of liability as stated in Contract Data part 1.
- X18.5
- Excluded matters that remain unlimited liability.
- X18.6
- Contractor only liable for matters notified before end of liability period.
X20 – Key Performance Indicators and Reporting Requirements
- X20.1-5
- As per CD1.
X21 Whole Life Cost
- X21.1
- Contractor can propose Scope change to reduce life cost of an asset.
- X21.2
- Contractor to submit quotation if SM prepared to consider change.
- X21.3
- Service Manager responds to quotation within period for reply.
- X21.5
- Service Manager changes Scope/Prices/revised plan accordingly.
X23 Extending the Service Period
- X23.1
- By agreement Service Period may extended to maximum service period.
- X23.2
- Criteria for extensions need to be met to allow extension.
X24 Accounting Periods
- X24.1
- Assessments made within 13 weeks of each accounting period.
- X24.2
- Service Manager assessments are conclusive unless dispute triggered.
Schedule of Cost Components (for use with options C/E)
- 11-14
- Payments applicable for people.
- 21-28
- Payments applicable for Equipment.
- 31-32
- Payments applicable for Plant and Materials
- 41
- Payments applicable for Subcontractors
- 51-53
- Cost of charges paid or received by the Contractor.
- 61
- Cost of manufacture of Plant and Materials by Contractor.
- 71
- Shared services outside the Service Areas.
- 8
- Insurance premiums and insurable events excluded from cost.
Short Schedule of Cost Components (for use with options A)
- 11
- Payments applicable for people
- 21-27
- Payments applicable for Equipment.
- 31/32
- Payments applicable for Plant and Materials.
- 41
- Payments applicable for Subcontractors.
- 51-53
- Cost of charges paid or received by the Contractor.
- 61
- Cost of manufacture of Plant and Materials by Contractor.
- 71/72
- Contractor cost of design of works and Equipment outside Working Areas.
- 8
- Insurance premiums and insurable events excluded from cost.
Abbreviations
- CD1
- Contract Data part 1
- CD2
- Contract Data part 2
- SM
- Service Manger
- CE
- Compensation event
— Glenn Hide, 01/06/2026