NEC Downloads & Publications

NEC4 Engineering and Construction Short Subcontract (ECSS) High Level User Guide

Introduction

This NEC4 Engineering and Construction Subcontract (ECSS) high-level overview is intended to be a quick reference guide as to where a particular subject matter can be found within the contract. This guide focuses on the most used and day to day clauses likely to be most relevant. For a specific project, any bespoke clause amendments introduced by a Subcontractor would have to be taken into account.

With this particular contract the first section to be filled in is all the elements of Contract Data. This includes:

  • Contractor’s Subcontract Data
  • Subcontractor’s Subcontract Data
  • Subcontractor’s Offer and Contractor’s Acceptance
  • Price List
  • Scope
  • Site Information

It is worth noting that Scope is further divided into separate sections again all of which need completing before entering into a signed agreement:

  1. Description of the Works
  2. Drawings
  3. Specifications
  4. Constraints on how Subcontractor provides the Works
  5. Requirements for the Programme
  6. Services and other things provided by Contractor

Section 1 – General                     

Actions

10.1      Reminder that all Parties are to act as stated in the contract.

10.2      Obligation to also act in a spirit of mutual trust and cooperation.

Defined Terms

11.2      16 no. listed in alphabetical order.

Communications                              

13.1      All communications issued in a form that can be read, copied and recorded.

13.2      Responses within period for reply or as stated in contract.

Project Manager                                 

14.1      Subcontractor obeys written instructions given by Contractor.

14.2      Contractor can issue instructions to change the Scope.

14.3      Contractor gives an instruction to correct a mistake in Price List.

14.4      Contractor acceptance of a communication does not change Subcontractor liability.

Early Warnings

15.1       Reasons for which an early warning should be notified.                          

15.2       Both Parties co-operate in considering proposals to avoid or reduce the risk and deciding actions.

Access to site

16.1      Contractor allows access to site as necessary for the work.

16.2      Contractor provides services and other things as stated in the Scope.

Corrupt Acts                                          

17.1      Subcontractor does not do a Corrupt Act.

Section 2 – Subcontractor’s Responsibilities

Providing the Works                         

20.1      Subcontractor obligation to Provide the Works in accordance with Scope.

20.2      Subcontractor does not start work which Subcontractor has designed, until Contractor has accepted.

Subsubcontracting and people

21.1      Subcontractor responsible to provide the works whether or not it has been subsubcontracted.

21.3      Contractor may instruct Subcontractor to remove a person within one day from instruction.

Access for the Contractor

22.1      Subcontractor provides access to work being done and to stored Plant and Materials.

Section 3 – Programme

Starting, Completion and programme

30.1      Subcontractor does not start work on site until starting date and completes work by Completion Date.

30.2      Subcontractor submits weekly forecast of the date of Completion.

30.3      Contractor decides date of Completion and certifies within 1 week.

30.4      Contractor may instruct Subcontractor to stop or not start work, and to re-start or remove from Scope.

31.1      Subcontractor submits programme as stated in Scope

Section 4 – Quality Management

Tests and Inspections

40.1      Requirement to carry out tests and inspections as per Scope.

Searching/Notifying Defects

41.1      Contractor can instruct Subcontractor to search for a defect.

41.2      Contractor can notify a defect up until the defects date.

Correcting Defects

42.1      Subcontractor obligation to correct a defect.

42.2      Before Completion defects corrected within a timescale to avoid impact Contractor or others.

42.3      After Completion defects corrected within defect correction period.

42.4      Contractor obligation and timing to issue Defects Certificate.

Accepting Defects

43.1      Can propose for defect to not be corrected and Scope changed accordingly for reduced Prices.

Uncorrected Defects

44.1      Contractor can assess costs of uncorrected defects and charge Subcontractor.

Section 5 – Payment

Assessing the Amount Due

50.1      Contractor to assess the amount due at each assessment day.

50.2      Subcontractor to include in application explanation of build-up.

50.4      If Subcontractor does not submit application on time, it will be assessed as zero that period.

50.5      Contractor may make own assessment of application if they consider one submitted to be incorrect.

50.6      Subcontractor liable for delay damages for each day beyond Completion Date.

50.7      Retention amount will be withheld from applications and paid upon Completion/Defect Certificate.

50.8      25% PWDD can be withheld if no 1st programme issued showing information Scope requires.

Payment

51.1      Payment made within 3 weeks of assessment date and is a cumulative application.

51.2      Interest recoverable on late or corrected items. 

Section 6 – Compensation Events

Compensation Events

60.1      List of what events would be valid compensation events (12 reasons).

60.2      Any ambiguity in Site Information favours Subcontractor.

Notification

61.1      Contractor or Subcontractor may notify a compensation event.

61.2      Subcontractor submits quote within one week if Contractor notifies, or includes quote in their notification.

61.3      Subcontractor may be time barred if not notifying compensation event within three weeks.

Quotations

62.1      Subcontractor can state assumptions upon which quotation is based.

62.2      Contractor replies to quotation within period stated in Subcontract data.

62.3       Non-response to quotation within contractual timescales means deemed acceptance.

62.4      Contractor assesses quotation within one week if Subcontractor does not issue on time.

62.5      Contractor may state assumptions if assessing the quotation value which may then be corrected later.

Assessment

63.1      Price List used for compensation events that only change quantity.

63.2      Other events will be assessed upon actual/forecast Defined Cost.

63.3      Rates or lump sums may be used by agreement to assess compensation events.

63.5      New People Rates by agreement or by Contractor assessment for any missing categories.

63.7      Risk may be included within quotation and requires Subcontractor to react promptly to event.

63.8      Details how ambiguities will be assessed in terms of a compensation event.

63.10    Confirms agreed compensation events not revised.

 Section 7 – Title

70.1      Subcontractor has no title to anything found/existing on the site.

70.2      Subcontractor has title to materials from excavation and demolition.

Section 8 – Risks and Insurance

80.1      List of Contractor’s liabilities.

81.1      List of Subcontractor’s liabilities.

82          Recovery of costs between Subcontractor/Contractor.

83          Insurance policies and who needs to provide what to whom.

 Section 9 – Termination

90.1      List of valid reasons for termination.

91          Procedures to follow upon termination.

92          Payment rules upon termination.

93          Dispute resolution adjudication process and rules.