NEC3 & NEC4 Guidance Notes & Free NEC Downloads, NEC Training and NEC Events by GMH Planning Ltd

ECC Section 36 – Acceleration

The acceleration provisions  are actually very simple under the contract and are the mechanism for bringing forward the Completion Date at the request of the Project Manager to encourage an earlier completion. In very simple terms when dealing with compensation events, the Contractor is obliged to mitigate delay (do things differently but at no cost […]

  • Programme NEC guidance category
NEC3 & NEC4 Guidance Notes & Free NEC Downloads, NEC Training and NEC Events by GMH Planning Ltd

ECC Clause 32.1 – Revising the Programme

This clause requires that all subsequent programmes include actual progress achieved on each operation and effect upon remaining work, , how Contractor plans to deal with delays and correct notified defects and any other changes that the Contractor proposes to make. NEC4 has deleted the requirement stated in NEC3 to also show on a revised […]

  • Programme NEC guidance category
NEC3 & NEC4 Guidance Notes & Free NEC Downloads, NEC Training and NEC Events by GMH Planning Ltd

ECC Clause 31.3 – Programme Acceptance

The Accepted Programme is key in agreeing the true state of play at any one point in time for that project. The regularly submitted programmes will include Contractor’s progress, their planned sequence of activities, as well as the effect that compensation events have at the time that they occur. The maximum period between programme submissions […]

  • Programme NEC guidance category
NEC3 & NEC4 Guidance Notes & Free NEC Downloads, NEC Training and NEC Events by GMH Planning Ltd

ECC Clause 31.2 – Programme Requirements

This clause is indeed one of the longest in the whole Contract, which provides a comprehensive list of what should be included within each programme issued for acceptance. It includes: – starting date, access dates, Key Dates and Completion Date – planned Completion – order and timing of the operations which Contractor plans to do […]

  • Programme NEC guidance category
NEC3 & NEC4 Guidance Notes & Free NEC Downloads, NEC Training and NEC Events by GMH Planning Ltd

ECC Clause 31.1 – Programme

Clause 31.1 confirms that a programme can either be bound into the contract or a first programme issued for acceptance after contract award within the time scales indicated within contract date part 1. If a programme is incorporated into the contract then this in effect becomes the first accepted programme. In practical terms it is […]

  • Programme NEC guidance category
NEC3 & NEC4 Guidance Notes & Free NEC Downloads, NEC Training and NEC Events by GMH Planning Ltd

ECC Section 3 – Programme

The NEC suite of contracts puts far greater contractual requirements upon the Contractor to produce and manage a detailed programme than other forms of contract currently in existence within the construction industry. Clear contractual mechanisms for agreeing change between the parties are key to successs.

  • Programme NEC guidance category