title: Programme effects of an early warning
date: 2010-07-10T19:34:49Z
modified: 2024-03-01T09:49:26Z
permalink: "https://gmhplanning.co.uk/nec-downloads/programme-effects-of-an-early-warning/"
type: downloads
status: publish
excerpt: NEC3 used to require that the effect of notified early warnings should be shown on a programme issued for acceptance, before that requirement was deleted in the June 2006 amendments. What does this mean in terms of what should be shown on the programme in terms of early warnings?
wpid: 1613
nec_contract_type:
  - NEC3
nec_contract_version:
  - NEC Engineering & Construction Contract (ECC)
download_category:
  - Early warnings
  - Programme
featured_image: "https://gmhplanning.co.uk/wp-content/uploads/2022/01/NEC3-and-NEC4-Downloads.png"
featured_image_alt: ECSS
author: Glenn Hide
timestamp: 2024-03-01T09:49:26Z
tags:
  - NEC3
  - NEC Engineering & Construction Contract (ECC)
  - Early warnings
  - Programme
---

NEC3 used to require that the effect of notified early warnings should be shown on a programme issued for acceptance, before that requirement was deleted in the June 2006 amendments. What does this mean in terms of what should be shown on the programme in terms of early warnings?

[Newsletter 39 – Programme effects of early warnings](http://gmhplanning.co.uk/wp-content/uploads/2011/10/Newsletter-39-Programme-effects-of-early-warnings.pdf)

## Topics

**NEC Contract Editions:** [NEC3](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/nec_contract_type/nec3.md)

**NEC Contract Versions:** [NEC Engineering & Construction Contract (ECC)](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/nec_contract_version/nec-engineering-construction-contract-ecc.md)

**Download Categories:** [Early warnings](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/early-warnings.md), [Programme](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/programme.md)