title: NEC4 ECSC - Detailed review of NEC4 Engineering and Construction Short Contract changes from NEC3
date: 2017-08-09T20:30:39Z
modified: 2024-03-01T09:49:14Z
permalink: "https://gmhplanning.co.uk/nec-downloads/nec4-ecsc-detailed-review-changes-nec3/"
type: downloads
status: publish
excerpt: ""
wpid: 2082
nec_contract_type:
  - NEC4
nec_contract_version:
  - NEC Engineering and Construction Short Contract (ECSC)
download_category:
  - Compensation events
  - Contract data
  - Early warnings
  - Payments
  - Programme
  - Quality / defects
  - Responsibilities
  - Terms and communications
featured_image: "https://gmhplanning.co.uk/wp-content/uploads/2017/08/NEC4-Engineering-and-Construction-Contract-Short-Contract-ECSC-e1649098238321.jpg"
featured_image_alt: NEC4 Engineering and Construction Contract Short Contract ECSC
author: Glenn Hide
timestamp: 2024-03-01T09:49:14Z
tags:
  - NEC4
  - NEC Engineering and Construction Short Contract (ECSC)
  - Compensation events
  - Contract data
  - Early warnings
  - Payments
  - Programme
  - Quality / defects
  - Responsibilities
  - Terms and communications
---

Here is the GMH Planning detailed guide as to the most important changes within the new NEC4 version of Engineering and Construction Short Contract. If you are fairly familiar with the NEC3 version then you will find this guide a very useful summary as to what you need to know is different within NEC4.

Each of these guides have now all been colour coded so that for each change identified it is split into one of five categories for easy reference: 1) new NEC4 clause, 2) new point of clarity, 3)Change to previous wording, 4) Same clause re-numbered, 5) Deleted NEC3 clause

[NEC4 ECSC Comparison Document](https://gmhplanning.co.uk/wp-content/uploads/2017/11/NEC4-ECSC-Comparison-Document.pdf)[Download](https://gmhplanning.co.uk/wp-content/uploads/2017/11/NEC4-ECSC-Comparison-Document.pdf)

## Topics

**NEC Contract Editions:** [NEC4](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/nec_contract_type/nec4.md)

**NEC Contract Versions:** [NEC Engineering and Construction Short Contract (ECSC)](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/nec_contract_version/nec-engineering-and-construction-short-contract-ecsc.md)

**Download Categories:** [Compensation events](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/compensation-events.md), [Contract data](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/contract-data.md), [Early warnings](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/early-warnings.md), [Payments](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/payments.md), [Programme](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/programme.md), [Quality / defects](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/quality-defects.md), [Responsibilities](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/responsibilities.md), [Terms and communications](https://gmhplanning.co.uk/wp-content/uploads/wp-mfa-exports/taxonomy/download_category/terms-and-communications.md)