Clause 61 – Notifying Compensation Events

Published: October 12th, 2011

It is not uncommon for people to take a literal meaning of clause 32.1, that a revised programme should show implemented compensation events. Their response has been that therefore that you do not show non-implemented compensation events. Is this actually the case? NEC3 June 2006 amendments also removed the clause that had previously stated that notified early warning matters should be included within the revised programmes. This could further cloud what, other than implemented compensation events, should be shown on the programme? 

It is important to remember with the contract that you often need to read more than one clause to get the true picture. Indeed, the other clauses in 32.1 make it clear that the programme should be showing the revised effect of all programme activities. Indeed – the prime function of the programme is to show us the true picture of the remaining works to be executed and (if nothing else changes) the Contractors planned completion date in relation to the Completion Date. It is clear under the contract that a compensation event only becomes implemented when you have agreed the cost or the PM has made his final assessment. You may therefore have already completed the work whilst the cost has not yet been agreed, hence under a dictionary definition you may feel you have “implemented” the work but contractually you have not. 

The programme should be a real management tool that reflects all programme activities and their relative effects upon each other. As soon as a compensation event is notified – it will more often than not be affecting the remaining works in some way and should therefore appear on the programme. Early on in the process it may not be clear the extent of the impact or duration that this additional activity will have – but each programme you produce you simply update that activity with the information you know at that point. The simple approach I take is to show the minimum impact that I know that activity will have at this point in time. This way you are not putting in too many activities that would otherwise artificially be pushing out the completion dates, only to come back at a later date as the activity does not have as bad an impact. For example, if planning approval for a compensation event will be a minimum three weeks but could be six weeks, it should show three weeks for now as it will definitely have that effect, and show any further delay as and when that becomes apparent.  

The last line of clause 61.1 states that the Contractor puts the instruction into effect. This importantly confirms that whilst a quotation has been requested and will be produced, in the meantime the Contractor starts to arrange for and carry out those works. This will include carrying out design, procuring materials, producing documentation as well as doing the physical works on site. Too many Contractors think that if they have been asked for a quote even under 61.1 that they will not do anything in terms of starting anything to do with that work until the quote has been agreed. 

Clause 61.2 allows a Project Manager to ask for proposed quotations – for events that he does not yet know if he wants for sure. In many instances it will depend on the price that the Contractor comes up with or the programme effect that it will have as to whether it is something the Project Manager wishes to proceed with. 

Clause 61.3 makes it very clear that in the absence of the Project Manager notifying a compensation event then the Contractor can notify. This then triggers the shortest response time in the whole of the contract for the Project Manager, who has to respond with a “yes” or a “no” as to whether that they agree it is a compensation event. If they answer is a “no” then under clause 61.4 they advise the Contractor of their decision (together with reasons).

Clause 61.5 clarifies that if the Project Manager feels that the Contractor did not give an early warning which an experienced contractor could have given, then he clarifies this at the point of requesting a quote. The significance of this is that the Project Manager can then assess the subsequent compensation event as though they had raised it, and possibly assess it at a lower value accordingly (see clause 63.5).

 

 


Did you know GMH Planning run Professional NEC Training Courses, free NEC3 conferences, and provide Expert NEC Consultancy?

« ECC Clause 60.1 – Compensation Events ECC Section 2 – Contractors main responsibilities »
If you found this post useful, please share it now.

About the Author: Glenn Hide

Glenn Hide has written 26 NEC related blog posts.

Glenn Hide is widely recognised within the construction industry as one of the leading NEC3 Contract and Project Planning experts. He brings over 15 years of experience working in the construction industry on a wide variety of construction projects, most of which for the Birse Group. His areas of expertise are Planning and Project Management, having been involved in the full lifecycle of many very large construction projects from inception to close out and in particular, successfully controlled the planning, costs and project management of projects which have been exclusively under the NEC form of contract.

Comments are closed.